How to run a Scrum of Scrums meeting

A Scrum of Scrums meeting is a short, Daily-Scrum-style meeting between teams that build one product. A representative from each team shares what affects the others: impediments, dependencies and anything that puts a Sprint Goal at risk. The Scrum@Scale Guide calls the event the Scaled Daily Scrum and time-boxes it to 15 minutes or less.

What a Scrum of Scrums is

People use the name for two things. In the Scrum@Scale Guide, a Scrum of Scrums is a team of teams: a group of Scrum Teams that must coordinate to deliver one integrated product each Sprint.

The meeting most people mean is that group's daily event, which the guide calls the Scaled Daily Scrum. The LeSS framework describes the same idea as "a Daily-Scrum-like meeting between teams".

The Scrum Guide itself does not define either. It is written for a single Scrum Team and defines no cross-team meeting, so this one is an addition that some scaling approaches make.

What the meeting is for

The meeting exists so the group understands its collective progress and responds to impediments that teams raise. It is about work that crosses team lines, not each person's tasks.

The Scrum@Scale Guide describes it as a forum to discuss how teams can work together more effectively. It covers what has been done, what will be done, what is going wrong and why, and what the group will do about it.

Who attends

One person from each team is enough. The Scrum@Scale Guide names who must be there and how large the group should get.

  • At least one representative from each team. The Scrum@Scale Guide says any person or number of people from the participating teams may attend as needed.
  • The Scrum of Scrums Master, who is accountable for making sure the scaled events take place, are productive and positive, and stay within the time-box. One of the teams' Scrum Masters can fill the role, or a person dedicated to it.
  • Four or five teams. The Scrum@Scale Guide puts the optimal number of teams in a Scrum of Scrums there, and larger products group several Scrums of Scrums together.

The questions to answer

Here are two published question sets. Pick one, and change it when your group finds better questions.

SourceQuestions
Scrum@Scale Guide (examples)What impediments will stop a team reaching its Sprint Goal or affect the delivery plan? Is a team doing anything that will stop another team? Have new dependencies, or a way to resolve one, been discovered?
LeSSWhat did my team do that is relevant to other teams? What will my team do that is relevant? What are my team's obstacles that other teams should know about or can help with?

Cadence and length

The two frameworks differ on how often to meet. Our advice is to start with the cadence that matches how often your teams block each other, then adjust.

  • Scrum@Scale: the Scaled Daily Scrum mirrors the Daily Scrum, a daily event, and is time-boxed to 15 minutes or less.
  • LeSS: a Scrum of Scrums meeting is typically held two or three times per week.

What to record

The Scrum@Scale Guide does not prescribe notes for this event. We suggest keeping a short list that every team can read, because the people who need the outcome are mostly not in the room.

  • Each cross-team impediment, the team it blocks and who will act on it.
  • Each new dependency and the two teams involved.
  • Anything that needs to go to someone outside the group, and who is taking it there.

Example: four teams, twelve minutes

This example is illustrative. Four teams build one booking product: Web, Mobile, Payments and Platform. One person from each joins a call at 9:45, after the team Daily Scrums.

  • Payments: "Our refund endpoint slips two days. Mobile, that blocks your cancel flow."
  • Mobile: "We will build against the mock and switch on Thursday."
  • Platform: "The staging database upgrade is Wednesday at 14:00. Expect ten minutes of downtime."
  • Web: "Nothing that affects anyone else."
  • Recorded: one impediment with an owner, one dependency, one scheduled change.

After the meeting

We suggest representatives take the outcome back to their teams the same day. Impediments the group cannot remove go up a level.

In Scrum@Scale, that level is the Executive Action Team, which is accountable for removing impediments that members of the Scrum of Scrums cannot remove themselves.

When to think twice

Not every scaling approach uses this meeting. LeSS recommends against it and prefers that teams coordinate directly.

LeSS adds a caution worth reading before you add the meeting. The wish to hold one can be a sign of unnecessary dependencies, caused by single-function groups and component teams.

Its advice is practical all the same: if the meeting is working, do not stop.

Where Bridge fits

If nobody in a 15-minute meeting wants to be the note taker, Bridge can take the notes. That works whether you host the meeting on Bridge or capture a Zoom, Google Meet or Microsoft Teams call.

  • After the meeting, the Notes tab holds a summary, decisions and follow-ups, with assigned action items when any were discussed.
  • File each day's meeting in one Space and share it, so every team can open the notes without attending.