Shift handover in manufacturing: pass on what the next shift needs

In manufacturing and process plants, shift handover is a point where safety-critical information can get lost, and UK HSE links many accidents to it. HSE guidance says handover should be face to face, two-way, spoken and written, and given as much time as it needs. Plan it around what the incoming shift needs to know, not what the outgoing shift remembers.

Why handover deserves a real meeting

The UK Health and Safety Executive (HSE) says many accidents have followed failures of communication at shift handover. Most of them involved planned maintenance work.

HSE gives two examples. In the 1983 Sellafield beach incident, radioactive waste was discharged to sea after a failure of communication between shifts. The Cullen Report also named handover failures as one factor in the Piper Alpha disaster.

The three parts of a handover

HSE describes effective handover as three steps, not one conversation:

  • Preparation by the outgoing shift.
  • The handover itself, where outgoing and incoming staff exchange task-relevant information.
  • Cross-checking by the incoming shift as it takes over responsibility.

Spot the higher-risk handovers

HSE's inspection guidance flags these situations for extra care. Give them more time and a written record:

  • Maintenance that continues over a shift change.
  • Safety systems that have been overridden.
  • Deviations from normal operation.
  • Someone returning after a long absence.
  • Handovers between experienced and inexperienced staff.

How to run it

HSE says handover should be face to face and two-way, with both people sharing responsibility for accuracy. It should use spoken and written communication and get as much time as it needs.

HSE also advises relying more on written communication when 12-hour shifts are in operation. Where possible, plan maintenance so it finishes within one shift.

An example handover checklist

HSE recommends basing handover on an analysis of what incoming staff need to know. This illustrative checklist shows the kind of list that analysis might produce for one process line:

  • Current plant status and anything running outside normal limits.
  • Open permits to work and maintenance in progress, with who holds each one.
  • Any safety system that is bypassed or overridden, why, and when it will be restored.
  • Alarms or faults seen this shift and what was done.
  • Jobs the incoming shift must start, finish or check, and by when.
  • Questions the incoming lead asked, and the answers, before they sign off.

Improve the process with the people who use it

HSE suggests designing logs and displays around what operators need, and involving end users when you change handover methods. Ask each shift lead which items they most often have to chase after a handover, and add those to the checklist.

Keep a record of spoken handovers with Bridge

A face-to-face handover can still leave a written trail. Record it in the room with the Bridge web app or Mac desktop app, using a microphone that can hear both people.