How to run a go/no-go meeting before a launch
A go/no-go meeting is the last checkpoint before a launch. Each owner reports whether their area is ready against criteria agreed in advance, then the group is polled. NASA's flight readiness review and Google's launch reviews show how to do it. This page gives an agenda, the decision options and an example.
What a go/no-go meeting is
A go/no-go meeting decides one thing: does the launch proceed as planned? It is not a status update and not a design review. The work should be done before people walk in.
NASA's version is the flight readiness review. NASA's engineering requirements say it examines the tests, demonstrations, analyses and audits that determine readiness for a safe and successful flight or launch.
The same review also checks that hardware, software, personnel and procedures are operationally ready. That list is worth copying: a launch can be blocked by people and procedures as easily as by code.
Agree the criteria before the meeting
A poll only works if everyone knows what "go" means. One of NASA's success criteria for the review is that the system state supports a launch "go" decision based on the established go/no-go criteria.
Established is the key word. Write the criteria when you plan the launch, not in the room.
Google's Site Reliability Engineering book describes the tool it uses for this: a launch checklist of common questions to ask about a launch. It suggests structuring a new checklist around broad themes such as reliability, failure modes and processes.
- Give each criterion one owner who will answer for it in the meeting.
- Phrase each one so the answer is yes or no: "Rollback tested in staging", not "Rollback looks fine".
- Keep the list short. Google's book notes that a checklist can grow to an unmanageable size and needs careful curation.
When to hold it and who attends
Hold it close enough to launch that the evidence is current, and early enough that a "no-go" can still be fixed. Google's launch reviews became common practice days to weeks before a launch.
Invite one owner for each criterion, the person who makes the final call and whoever will run the launch itself. Keep observers out of the poll.
| Role | What they do in the meeting |
|---|---|
| Decision owner | Runs the poll and makes the final call |
| Area owners | Report go or no-go for their criteria, with evidence |
| Launch lead | Confirms the plan, timing and rollback |
| Note taker | Records each answer, each open item and each condition |
A 30-minute go/no-go agenda
| Minutes | Item | Output |
|---|---|---|
| 0 to 3 | Restate what is launching, when, and the criteria | Everyone is answering the same question |
| 3 to 15 | Each owner reports against their criteria | A yes or no per criterion |
| 15 to 22 | Open items and exceptions | Each one closed, accepted as a risk or made a condition |
| 22 to 26 | The poll: each owner says go or no-go | A recorded answer per owner |
| 26 to 30 | Decision, conditions and next check | Go, go with conditions, or no-go with a date to meet again |
Handle open items in the open
Few launches arrive with nothing open. NASA's criteria allow for that: open items and waivers have been examined, and the residual risk from them is deemed acceptable.
That gives you three honest options for each open item. Close it before launch, accept the risk by name, or make it a condition of going.
NASA's own announcements show the third option in use. After the Artemis II flight readiness review, NASA said teams polled "go" to proceed toward launch, pending close out of remaining open work.
Record the decision so it holds
The record should let someone who missed the meeting see what was decided and what still has to happen.
- The decision: go, go with conditions, or no-go.
- Each owner's answer, by name.
- Each condition, with an owner and a deadline before launch.
- Each accepted risk, and who accepted it.
- For a no-go: what must change, and when the group meets again.
Example: a billing migration
This example is illustrative. Northwind, a fictional software company, plans to move customers to a new billing system on Thursday. The decision owner is the head of engineering.
Five owners report. Four say go. The support lead says no-go: the help articles for the new invoices are not published.
The group makes it a condition instead of a delay. The record reads: "Go with one condition. Help articles published by Wednesday 5 pm, owner Priya. If not, launch moves to Monday." Priya confirms on Wednesday, and the launch proceeds.
Where Bridge fits
The poll is spoken, and the conditions are usually agreed in a sentence. That is easy to lose. Bridge keeps the meeting side of the record:
- Capture: host the meeting on Bridge, or capture a Zoom, Google Meet or Microsoft Teams call with an external agent the host admits. The Mac desktop app records without a bot.
- Notes: each meeting gets structured notes with a summary, decisions and follow-ups.
- Transcript: the speaker-labeled transcript shows who said go, in their own words.
- Action items: conditions assigned in the meeting appear in the notes and in the Action items list on Home, each with an assignee you can edit.
Limits to keep in mind
- NASA's review is built for spaceflight and Google's checklist for large web services. Borrow the structure, and size it to your launch.
- The agenda, roles and example on this page are our suggestions, not NASA's or Google's.
- A unanimous go does not remove risk. It records that the people responsible judged the remaining risk acceptable.
- Check AI-written notes against the transcript before you rely on a recorded condition or deadline.
Sources & further reading
- NASA Procedural Requirements 7123.1D, Appendix G: Life-Cycle and Technical Review Entrance and Success Criteria ↗
- NASA: Artemis II Flight Readiness Polls Go to Proceed Toward April Launch ↗
- Google, Site Reliability Engineering: Reliable Product Launches at Scale ↗
- Bridge help center: Notetaking ↗
- Bridge help center: Capture a virtual meeting outside Bridge ↗